SeAH Drive Extension and Cedar Creek Lift Station Improvements
Infrastructure improvements including the SeAH Drive road extension and upgrades to the Cedar Creek Lift Station and Force Main are up for design contract approval to support local growth.
The Link Utilities and Storm Improvements
A proposed $580,358.29 construction contract with Bell Contractors, Inc. was scheduled for review to handle essential utility and storm drainage work for 'The Link' project.
Fire Station Improvements
The city is upgrading its fire fleet with new apparatus and planning major station upgrades and relocations, such as Stations 7, 9, and 2, to improve coverage and response times.
Friars Creek Detention Pond Project
Unanticipated buried concrete and construction debris at the Friars Creek Detention Pond site require soil removal and a contract change order of $107,187.50.